Comcast is planning to launch an Advanced Fiber Network project in Louisville beginning in late May 2018. This multi-month engineering and construction project will bring fiber optic infrastructure deeper into Louisville neighborhoods. City-wide in scope, the project involves a combination of construction in the public right-of-way and easements, installation of new and upgraded equipment and changes to the network architecture.

Construction & Notifications

The majority of Comcast's construction work will occur in the public right-of-way and easements. On the limited occasions where Comcast needs to access private property, it will contact residents directly to obtain their approval before initiating any work.

As part of this process, Comcast will provide multiple notifications to residents and businesses in advance of any construction impacting their neighborhood or commercial area. For residents, this includes door hangers, notification letters, direct phone calls and text messages the day of construction. For businesses, Comcast will reach out directly 7-10 days in advance of the work.

When Comcast anticipates a service interruption associated with the network upgrade, it will provide additional notification to both residents and businesses.

Timeline

Comcast and its business partners will begin their work in late May. Below is the estimated timeline and general location of the work. See the map for the specific node servicing your neighborhood:

NODE

Construction Start/End Date

Cut/Activation Start/End Date

LU01

May 25, 2018/July 5, 2018

August 8, 2018/August 10, 2018

LU02

In progress/June 30, 2018

July 30, 2018/August 2, 2018

LU10

May 30, 2018/July 5, 2018

July 25, 2018/July 27, 2018

LU05

Permit pending

August 2, 2018/August 7, 2018

LU06

Permit pending

August 16, 2018/August 21, 2018

LU08

Permit submittal June 1, 2018

August 13, 2018/August 15, 2018

LU03

Permit submittal June 1, 2018

August 22, 2018/August 27, 2018

LU09

Permit submittal June 1, 2018

August 24, 2018/August 28, 2018

LU07

June 13, 2018/July 20, 2018

August 28, 2018/August 31, 2018

LU04

June 4, 2018/July 13, 2018

September 4, 2018/September 6, 2018

LU13

August 1, 2018/August 16, 2018

September 7, 2018/September 10, 2018

***Note: dates are estimated and subject to change 