Construction Updates

Print
Press Enter to show all options, press Tab go to next option

2018 City Construction Project Map

PW Map

To view the 2018 City Construction Project Map, click here. This construction schedule is tentative and subject to change due to construction coordination, unknown site conditions, and weather. 

Street Resurfacing Project

APC Construction Company, LLC has substantially completed the work.  Remaining work includes cleanup and repair of deficiencies. 

Concrete Replacement Project

Norra Concrete Company has substantially completed the work.  Remaining work includes cleanup and repair of deficiencies.  

Street Reconstruction Project

Asphalt Specialties Company is the contractor for the project.  The Work consists of the demolition, asphalt removal, subgrade shaping and material processing, asphalt paving, pavement marking and traffic control within subdivisions and/or on specified streets.  Tentative construction schedule is early July thru late August. 

Location Description Tentative Construction Schedule
Walnut Street from Lincoln Ave. to McKinley Ave.,  Week of August 20 - Asphalt Paving of Top Mat
Garfield Ave. dirt work from Pine St. to North Alley Top Mat Paved
 McKinley Ave.  from Pine St. to North Alley and portion of Walnut west of McKinley

Top Mat Paved

 Sunset Dr.  from S. Boulder Rd. to Jefferson Ave.  Week of August 20 - Asphalt Paving of Top Mat
 Longs Peak Ave.  from S. Boulder Rd to Sunset Dr.

 Week of August 20 - Asphalt Paving of Top Mat

 Hoover Ct,  S. Carter Ct., Raintree Ct.

   Week of August 20 and 27

Pavement Crack Seal Project

CKC Asphalt Services is the contractor for the project.  Due to the hot weather and application issues the work is rescheduled to occur in late September or early October.  

2018 Water Main Replacement Project 

BEC Construction was awarded the project.    Work on Lafayette St. at Franklin Ave./Ct. continues until the end of August.   See above maps.

2018 Sanitary Sewer Main Replacement Project

The contract was awarded to Excavation & Construction Specialty.  Construction has begun in the alley west of Grant Ave. north of Walnut St.  See the map above for locations.

2018 Storm Sewer Maintenance Project

The project was awarded to Rocky Mountain Water Works. Work in the alley north of Pine St. west of the BNSF Rairoad tracks and Bella Vista & County Road is scheduled the week of August 20-25

2018 Contract Striping Project

The project was awarded to American Striping.  Work has begun and will continue through the end of August.

Downtown Construction

The South Street Underpass, is completed.

We would like to thank everyone for your patience and understanding during construction and remind everyone to exercise caution when driving, biking, or walking through a construction zone.