Construction Updates

Print
Press Enter to show all options, press Tab go to next option

2018 City Construction Project Map

PW Map

To view the 2018 City Construction Project Map, click here. This construction schedule is tentative and subject to change due to construction coordination, unknown site conditions, and weather. 

 

2018 Water Main Replacement Project 

BEC Construction was awarded the project.    Work is substantially complete.  Contractor working on punch list and on close out documents.   See above maps.

2018 Sanitary Sewer Main Replacement Project

The contract was awarded to Excavation & Construction Specialty.  Work is substantially complete.  Contractor working on punch list and close out documents.  See the map above for locations.

2018 Storm Sewer Maintenance Project

The project was awarded to Rocky Mountain Water Works. Work is substantially complete.  Contractor working on punch list and close out documents.

2018 Contract Striping Project

The project was awarded to American Striping.  Work has begun and will continue through mid November.

2018 Downtown Paver Repair

Concrete and brick paver repair work will commence in early December at various locations in the Downtown.

2018 SCWTP Plate Settlers

Starting in December, the City will be removing the tube settlers, a component of the sedimentation process, from the Sid Copeland Water Treatment Plant (SCWTP).  Following the removal, new more efficient and durable plate settlers will be installed, which have already been delivered to the site.  The removal and installation will utilize a construction crane to facilities these activities.  Project is anticipated to be complete by March 2019. 

We would like to thank everyone for your patience and understanding during construction and remind everyone to exercise caution when driving, biking, or walking through a construction zone.