Construction Updates

Print
Press Enter to show all options, press Tab go to next option

2018 City Construction Project Map

PW Map

To view the 2018 City Construction Project Map, click here. This construction schedule is tentative and subject to change due to construction coordination, unknown site conditions, and weather. 

Street Resurfacing Project

APC Construction Company, LLC (APC) is the general contractor.  The work consists of the demolition, asphalt milling, asphalt patching and leveling, hot chip seal, chip seal, slurry seal, pavement marking and traffic control within subdivisions and/or on specified streets.  Work will require no parking on streets receiving treatment between 7:00 a.m. and 5:00 p.m.  Contractor will place no parking signage 24 hours in advance. One lane traffic will be provided under flagger control.  Access to side street controlled by flagger.  One lane traffic will be provided under flagger control. Please drive with caution through the construction zone.  Tentative work schedule is as follows:

Location Description Schedule
Washington Ave. Asphalt Leveler Course Week of June 18
" Chip Seal Week of July 2
" Hot Chip Seal Week of July 9 or 16
Centennial Valley Asphalt Leveler Course Week of June 25
" Chip Seal Week of July 2
Ridgeview Estates Chip Seal Week of July 2
Enclave Cr., Enclave Way, W. Pine Ct., W. Dahlia St., Madison Ave., and Polk Ave. Slurry Seal June 19 & 20, weather permitting


Concrete Replacement Project

Norra Concrete Company has completed the base contract.  Replacement and deficiencies in work will be completed later this summer.

Street Reconstruction Project

Asphalt Specialties Company is the contractor for the project.  The Work consists of the demolition, asphalt removal, subgrade shaping and material processing, asphalt paving, pavement marking and traffic control within subdivisions and/or on specified streets.  Tentative construction schedule is late June thru September.

Pavement Crack Seal Project

CKC Asphalt Services is the contractor for the project.  Due to the hot weather and application concerns the work is rescheduled to occur in late September or early October.  

2018 Water Main Replacement Project 

BEC Construction was awarded the project on May 1st.   Work has started on Hoover Ave. and will continue until mid June.  Work on Johnson Ave. will begin in late June/early July.  See above maps.

2018 Sanitary Sewer Main Replacement Project

The project bid on May 17th.  The contract will go to Council on June 19 (Excavation & Construction Specialty is the apparent low Bidder).  Construction will begin in early July and completed in September.  See the map above for locations.

Downtown Construction

The South Street Underpass, is open to the Public.  Contractor will repair handrails and concrete cap on landscape walls. 

 We would like to thank everyone for your patience and understanding during construction and remind everyone to exercise caution when driving, biking, or walking through a construction zone.