Construction Updates

Print
Press Enter to show all options, press Tab go to next option

2018 City Construction Project Map

PW Map

To view the 2018 City Construction Project Map, click here. This construction schedule is tentative and subject to change due to construction coordination, unknown site conditions, and weather. 

 

2018 Water Main Replacement Project 

BEC Construction was awarded the project.    Work is substantially complete.  Contractor working on punch list and on close out documents.   See above maps.

2018 Sanitary Sewer Main Replacement Project

The contract was awarded to Excavation & Construction Specialty.  Work continues with manhole repairs, patching and concrete replacement. See the map above for locations.

2018 Storm Sewer Maintenance Project

The project was awarded to Rocky Mountain Water Works. Work is substantially complete.  Contractor working on punch list and close out documents.

2018 Contract Striping Project

The project was awarded to American Striping.  Work has begun and will continue through mid November.

We would like to thank everyone for your patience and understanding during construction and remind everyone to exercise caution when driving, biking, or walking through a construction zone.