Construction Updates

Print
Press Enter to show all options, press Tab go to next option

City Construction Project Map

2019PWConstructionUpdatesThumbnail

To view the City Construction Project Map, click here. This construction schedule is tentative and subject to change due to construction coordination, unknown site conditions, and weather. 

2019 Concrete Replacement Project

City Council awarded the contract to Standard Concrete Inc.  The work is substantially complete.  Staff issued a Punch List  of deficiences to the Contractor for repair.

2019 Street Resurfacing Project

City Council awarded the contract to APC Construction Company, LLC (APC).  Work is substantially complete.  Staff will prepare Punch List of deficiences for the Contractor. 

2019 Street Reconstruction Project

City Council awarded the contract to PLM Asphalt & Concrete, Inc. The work is substantially complete.  Staff is performing inspection and will prepare Punch List of deficiences for the Contractor. 

2019  Water Main Replacement Project

The project was awarded to Brannan Construction Co.  Asphalt and concrete repairs continue on Ridgeview Dr. (Town Homes at Coal Creek) the week of November 18.  Staff will prepare Punch List of deficiencies for the Contractor.

SH42 Underpass Project

The project was awarded to Edge Contracting.  Construction will continue the week of November 18 that will create a pedestrian underpass between Hecla Drive and Summit View Drive underneath SH42.  Easterly lane shift in place to accommodate work on west side of SH42.

SH42 and Short Street Project

The project was awarded to Goodland Construction. Work includes storm sewer, curb and walk along west side of SH42, sanitary sewer main segment realignment and reconstruction of SH42 between Griffith St. and South St.   Project construction has commenced and will continue through May 2020.  Construction continues the week of November 18. 

 Gas Main/Service Improvements

 Xcel Energy is upgrading gas mains west of Downtown to improve system capacity and better service customers.  New gas main and service line construction will continue through December, weather permitting.  Work will occur on the following street segments:

  • South St. from Main St. to Lincoln Ave.
  • Lincoln Ave. from South St. to Spruce St.
  • Spruce St. from Lincoln Ave. to McKinley Ave.

We would like to thank everyone for your patience and understanding during construction and remind everyone to exercise caution when driving, biking, or walking through a construction zone.