Construction Updates

Print
Press Enter to show all options, press Tab go to next option

City Construction Project Map

2019PWConstructionUpdatesThumbnail

To view the City Construction Project Map, click here. This construction schedule is tentative and subject to change due to construction coordination, unknown site conditions, and weather. 

2019 Concrete Replacement Project

City Council awarded the contract to Standard Concrete Inc.  The project includes replacement of broken, settled and spalled public concrete improvements such as curb, gutter, curb cuts, walk, bike path, cross pan, inlet decks and handicap ramps at various locations. Contractor will work on Aspen Way at Roosevelt Ave. the week of July 22, weather permitting.

2019 Street Resurfacing Project

City Council awarded the contract to APC Construction Company, LLC.  The project consists of demolition, asphalt paving, milling, patching, leveling, hot chip seal, chip seal, pavement marking and traffic control, including all work appurtenant thereto, on various streets within the City of Louisville.  Construction on segments of Dillon Road (asphalt milling and leveling) will continue the week of July 22.  One lane each direction will be available to traffic within the construction zone.  Alternate route suggested. 

2019 Street Reconstruction Project

City Council awarded the contract to PLM Asphalt & Concrete, Inc. The project consists of demolition, asphalt paving and reconstruction, milling, patching, pavement marking and traffic control including all work appurtenant thereto, on various streets within the City of Louisville. Construction will begin on Spruce St. from Lincoln Ave. to alley west of McKinley the week of July 22, weather permitting.

2019  Water Main Replacement Project

The project was awarded to Brannan Construction Co.  Construction on Eisenhower Dr. and on Hutchinson Street the week of July 22.  See locations in above map.

2019  Sanitary Sewer Replacement Project

The project was awarded to E-Z Excavating, Inc.  Construction will begin work on Garfield Ave. south of Pine St. the week of July 22.  See locations in above map.

2019 Sewer Video Project

The City has contracted with High Country Pipe to provide video inspection of approximately  62,000 feet of sewer mains throughout the City.  Over the next couple of months, crews and trucks will be accessing the sewer system via manholes located in the streets, alleys or in public right-of-way.  

2019 Ditch Maintenance

The Goodhue and Davidson Ditch Companies will be conducting major cleaning and vegetation removal between 1) Garfield Ave. and Centennial Dr. and 2) Garfield Ave. and Main St.  The City will be partnering with the Ditch Companies activities to minimize the length of time for this disturbance.  Work is scheduled to begin mid July and continue for about 3 weeks and should finish in early August.  

 We would like to thank everyone for your patience and understanding during construction and remind everyone to exercise caution when driving, biking, or walking through a construction zone.